FOUNDATIONS

 

All the work before the foundation of the passive house was ready to be cast took about 3 weeks. It consisted in the preparing of the building site, in the moving of existing things like the terrace, the garden house and the dwell, and in the excavating.

 

Torsten is storing stone slabsTorsten is storing stone slabs used in the current terrace

Anton is removing the white gravel from the current terrace

Torsten is removing stone slabs from the current terrace

Anton 8 feet below is "undermining" the foundation of the old house

Anton is preparing for undercasting the old house

The earthmoving team at the end of the day

Now it is ready for casting the foundation of the old house . It is necessary to do so in order to prevent the old house from collapsing during the excavation.

back to top

We undercasted first the middle section of the gable of the old house

The new foundation is preventing the old house from collapsing

Then the west section...

At last the east section...

If we had to use a wheelbarrow to move the excavated soil, we should have been doing it 3000 times! And it would have been impossible to move both the garden house and the dwell! It was amazing doing it with the JCB digger...

back to top

The west part of the passive house got excavated

This is what it looked like during excavation

The dwell had to be moved: The JCB-digger pushed it!

We got a hole as big as a crater! You would think a meteorite has hit the ground!

The JCB-digger didn't do it all alone. A little help from Anton was needed

The garden house had to be moved too! The JCB-digger pushed it. Amazing!

During all the time where we were moving the dwell, we enjoyed the company of our 2 hens. They were not disturbed by the noise of the machine.

Almost ready for the casting of the base plate of the passive house

The big day came: The base plate had to be cast and the first wallstones to be laid. Now we can imagine the shape of the passive house!

back to top

Concrete was poured down onto the base. It was smoothed and stamped. Finally the first row of wallstones was laid

Anton found out quickly how to build a mould for the angle left in between

The foundation is ready now!

The first step is reached now! Follow the construction of the next step under the section "cellar"

back to top